2025-Nov-03

Asset Management Firm

Migrate from legacy MDM environment to Microsoft 365 Intune integrated with Apple Business Manager, implementing zero-touch deployment and conditional access policies to strengthen mobile device security posture.

  • Automated device enrollment via zero-touch deployment
  • Remote wipe capability for lost or stolen devices
  • Conditional access policies ensuring only security-compliant devices can access corporate resources
  • Coordinated scheduling and timely migration with minimal business disruption

2025-Oct-20

Healthcare Firm

Deploy mission-critical enterprise UPS system at a warehouse in Heiwajima to protect essential network infrastructure supporting distribution operations, with multi-floor installation and rapid issue resolution.

  • High-capacity lithium-ion Smart-UPS units with modular battery systems across server room and warehouse floors
  • Precision rack mounting with PDU integration and power verification
  • Network Management Card configuration enabling remote monitoring and alert management
  • Comprehensive startup service with operator training on emergency procedures
  • Same-day resolution of DOA battery modules through expedited RMA coordination
  • Full system validation and handover within 72-hour installation window

2025-Oct-01

Asset Management Firm

Migrate from hybrid Configuration Manager environment to cloud-native provisioning using Windows Autopilot, eliminating on-premises dependency and executing new device staging and rollout with pre-applied security policies.

  • Transition to cloud-native setup environment
  • Location-independent device deployment capability
  • Security policies pre-applied at delivery to end users
  • Coordinated scheduling and timely migration with minimal business disruption

2025-Sept-16

Healthcare Firm

Complete wireless network infrastructure deployment across warehouse facility, including AP installations, server rack setup, and printer port connections across multiple floors totaling 50 access points.

  • 50 wireless access points installed
  • 20 printer ports terminated and tested
  • Server rack relocation and installation on a separate floor with anchor mounting
  • Specialized freezer room antenna installation with panel-type hardware
  • Multiple CHINO unit connections (additional scope items)
  • Coordinated multi-vendor activities including construction team and facilities
  • Site-specific challenges resolved including cable routing and label discrepancies

2025-Sept-12

Medical Device Maker

Manage comprehensive IT equipment shutdown and startup during planned electrical infrastructure upgrades at a Tokyo distribution facility, ensuring zero data loss and business continuity across warehouse operations and administrative systems.

  • Pre-shutdown validation of all network equipment, servers, and endpoints
  • Coordinated power-down sequence for multi-floor infrastructure including server room equipment
  • Complete startup and verification of enterprise UPS system, network infrastructure, and production servers
  • Systematic testing of wired/wireless connectivity, VoIP phones, and multifunction printers
  • FAX send/receive functionality verification and time-recording system validation
  • Remote standby support for first business day post-maintenance

2025-Jul-31

Asset Management Firm

Led IT project management and infrastructure buildout for expansion to additional floor within same building, collaborating with client's global IT team to plan and execute user relocation within a single weekend.

  • Dual fiber-optic lines installed for primary and backup connectivity with redundancy
  • LAN cabling throughout expansion area
  • AV system deployment and office equipment installation
  • Full workstation setup enabling users to resume work immediately
  • Hands-on migration support for user floor relocation

2025-Jun-20

Asset Management Firm

Replace faulty meeting room HDMI media converter and cabling, installing new underfloor HDMI cable run and automatic Crestron switcher for improved AV connectivity and reliability.

  • Underfloor HDMI cable installation from IT cabinet to meeting table
  • Crestron HD-MD4X1-4K-E automatic HDMI switcher installation and mounting
  • Dual HDMI connection points with automatic input switching capability
  • System testing and configuration verification

2025-Jun-02

Asset Management Firm

Provide onsite IT support for major investor-facing event, managing pre-event validation and day-of operations for network connectivity, AV equipment, and presentation systems to ensure stable IT environment for executives and external attendees.

  • Pre-event validation of venue network connectivity
  • Day-of operations for AV equipment and presentation systems
  • Rapid issue resolution during event
  • Smooth event proceedings support

2025-Mar-01

Finance Firm

Perform IT equipment shutdown and restart, during annual planned building power outage.

  • Equipment check and shutdown
  • Perform 2400VA PBX replacement
  • Reconnection and startup
  • Old equipment removal from rack and decommissioning

2024-Nov-27

Asset Management Firm

Perform additional memory installation for redundant Cisco 8300 router as continuation of network infrastructure upgrade, coordinating with client network team for equipment removal, memory card installation, and system verification.

  • Memory card installation for second Cisco 8300 router
  • Network cable labeling and documentation before unracking
  • Equipment removal and precision memory module installation
  • System remounting with power and network reconnection
  • Network team verification of router operation and startup

2024-Oct-15

Finance Firm

Handle all aspects of IT for an urgent office move for a Tokyo-based startup, performing PM and vendor coordination.

  • Infra design emphasizing security but with superior cost-performance
  • Structured cable, system rack with environment monitoring and, redundant UPS and Internet
  • Fortinet firewalls, switches, and wireless
  • Poly IP desk phones connect to a voice gateway
  • Several conference rooms kitted with a Logitech VC system for Zoom meetings
  • Various end-user systems built and installed

2024-May-13

Law Firm

Handle all aspects of IT install or upgrade for office move in Tokyo, within the same building to consolidate space, performing project management and coordination of move vendors vis-à-vis IT, reporting to HQ IT.

  • Structured LAN cabling (floor and vertical)
  • Large, redundant UPS deployment
  • Wireless install and test
  • Network including site-to-site VPN to HQ and DC deployment
  • Phone system test after 3rd party migration
  • Multi-function printers install and test
  • Video conferencing system design, install and test
  • Physical security and CCTV system design, install and test
  • Various new peripherals for end-users and others

2023-Sept-01

Energy Management Control Solution Firm

Small office setup in Yokohama, including fiber line and ISP arrangements, mini-rack and UPS, Fortinet FortiWifi with VPN connection to client's infrastructure, Poly Teams Room videoconferencing, workstations, and Fujifilm printer / fax.

2023-Aug-25

Steel Wire Technology Maker

Relocated warehouse ceiling cables for wireless access points and printers, to factory office area, performed troubleshooting on one due to poor performance shown by cable test. Discovered water damage to cables, attempted to clean it up, and replaced cable as needed.

2023-Aug-25

Asset Management Firm

Install a dual display stand kit, mount displays, tidy up cables.

2023-Aug-07

Asset Management Firm

Deploy 3 Nutanix devices for cloud service unification.

2023-Jul-27

Energy Management Control Solution Firm

Coordinate site survey prior to NTT fiber line installation, take photos to show relevant site details.

2023-Jul-04

Law Firm

Steward removal of Colt fiber line and related equipment, tidy cables, update documentation.

2023-Jun-26

Steel Wire Technology Maker

Localized Japanese Language Website Launch

2023-May-26

Steel Wire Technology Maker

Perform IT equipment shutdown and restart, during annual planned building power outage, coordinate PBX maintenance, and remove old server and UPS equipment from rack for decommissioning.

2023-May-26

Asset Management Firm

Replace existing ceiling-mounted Cisco wireless access points, and deploy additional new one in data center.

2023-Apr-29

Medical Device Maker

Steward IT equipment power off and power up, and operational validation, for planned annual building power maintenance.

2023-Mar-31

Asset Management Firm

Replace ceiling-mounted wireless access point, patch to specific switch port, validate connectivity for guest and company Wifi. Additionally, trace LAN cable for a later task.

2023-Mar-19

Medical Device Maker

Shutdown and restart all IT equipment at warehouse / distribution center, due to planned annual power maintenance. Validate all IT and business operational functions for regular business starting the next day.

2023-Feb-11

Law Firm

Steward IT equipment shutdown and restart, during planned regular power outage at Tokyo site building. Remove decommissioned equipment, tidy up cables.

2023-Jan-24

Law Firm

Deploy 2 new FortiGate 101F firewalls and a new OpenGear to allow HQ IT remote access. Assist validation, then remove equipment to be decommissioned.

2022-Nov-11

Law Firm

Perform audio visual system demo, to evaluate difference between Logicool Rally Plus vs Rally Bar.

2022-Nov-07

Medical Device Maker

Steward shutdown and restart of IT equipment for annual planned building power cycle, then validate all business systems such as fax order entry.

2022-Oct-22

Asset Management Firm

Convert conference room video conferencing system from Cisco Webex Video to MS Teams, installing Lenovo ThinkSmart core kit for MS Teams and touchpad controller, ClearOne ceiling microphone, ceiling speakers, Huddly L1 camera and removing Webex all-in-one kit and its touchpad.

2022-Sept-29

Steel Wire Technology Maker

Install APC Smart-UPS 3000 RM UPS Replacement, including shutting down connected servers and devices, disconnect and reconnect, configure management card, re-start and validation.

2022-Sept-09

Asset Management Firm

Annual disaster recovery test, Bloomberg Software and Laptop imaging, pre- and post-failover.

2022-Sept-08

Law Firm

New edge router deployment and remote access console connection.

2022-Sept-03

Medical Device Maker

Re-mount existing wall-mounted conference room 75-inch monitor and install additional 43-inch monitor for AV system.

2022-Jul-30

Asset Management Firm

Cisco switch replacement work for DMZ security improvement.

2022-Jun-11

Analytical Instruments Maker

Perform Windows update patching for on-premise Servers, patch firmware on network and security devices.

2022-May-02

Asset Management Firm

Steward PBX migration to new model and desk phones.

2022-Apr-17

Medical Device Maker

Steward annual datacenter blackout over weekend, with IT equipment shutdown, restart and troubleshooting.

2022-Apr-12

Steel Wire Technology Maker

Warehouse core switch replacement project.

2022-Apr-06

Steel Wire Technology Maker

Tokyo office core switch replacement project.

2022-Apr-06

Medical Device Maker

Office ceiling-mount wireless access point swap to new model.

2022-Apr-05

Law Firm

Pulse security device outage and emergency replacement stewardship.

2022-Mar-21

Medical Device Maker

Japan distribution center Kardex Remstar shuttle deployment project - launch preparation (LAN, printers, desk moves).

2022-Mar-08

Law Firm

Supervised APC support vendor to replace the intelligence module in Symmetra UPS, and de-rack three devices for decommissioning.

2022-Feb-11

Analytical Instruments Maker

Windows Server update patching, Firewall and network device firmware updates.

2022-Jan-15

Asset Management Firm

Handle annual power outage shutdown and restart, troubleshooting door security, new UPS, PBX voicemail.

2022-Jan-15

Asset Management Firm

Steward annual building blackout, IT equipment shutdown, restart and troubleshooting.

2022-Jan-08

Medical Device Maker

Japan distribution center Kardex Remstar shuttle deployment project - LAN installation.

2021-Nov-29

Law Firm

Tokyo server room UPS battery and PDU troubleshooting - XR Frame and battery unit replacement.

2021-Oct-22

Asset Management Firm

Annual disaster recovery test - pre- and post-failure IT operations.

2021-Oct-21

Law Firm

Troubleshoot Server Room UPS battery problem after burning smell detected.

2021-Aug-26

Law Firm

"Local hands and eyes" assist for Cisco ISE software upgrade after breakfix.

2021-Aug-02

Healthcare Firm

Launch of website to allow registration by healthcare professionals nationwide to participate in order entry system, including site and page design, anti-spam security, database design, furigana-romaji conversion API development, invitation email, operational workflow design on backend.

2021-Jul-31

Medical Device Maker

Handle all aspects of office move to another building within Tokyo, including project management, and coordination of move, along with installs or upgrades to all IT infrastructure aspects, including LAN cabling, wireless, network, phone system, multi-function printers, video conferencing system.

2021-Jul-17

Medical Device Maker

Handle all aspects of office move in Tokyo, within the same building to downsize space, performing project management and coordination of move vendors vis-à-vis IT. Major activity was installations or upgrades for all IT infrastructure aspects, including LAN cabling, wireless, network including site-to-site VPN to HQ and DC, phone system, multi-function printers, video conferencing system, fax server system, various new peripherals for end-users and others.

2021-Jun-30

Law Firm

Handling urgent Cisco ISE device troubleshooting, warranty hardware breakfix and secure disposal.

2021-Feb-18

Law Firm

Backup storage server unexpected outage. Stewarded fix with hardware engineer to replace needed parts.

2021-Feb-08

Healthcare Firm

Completed major project to develop, test and launch an order entry system for physicians to order genetic tests online, based on our PROdb cloud database system.

2021-Jan-20

Medical Device Maker

Mini LAN construction for minor equipment rearrangement at warehouse.

2021-Jan-17

Steel Wire Technology Maker

Breakfix for server RAID array HDD hardware failure. Server is out of warranty, so we arranged an appropriate spare, purchasing from old stock for that model.

2020-Oct-21

Car Parts Maker

Japan network is unstable due to Dell switch hardware problems. Stewarded a replacement of the core switches over multiple troubleshooting sessions, with full IT functionality re-validation.

2020-Oct-15

Healthcare Firm

Build and Launch of localized marketing website, integration with eSolia cloud database PROdb.

2020-Sept-17

Real Estate Finance Management

Installation of new LAN Cabling on and between floors, to allow modern IP phone system to be deployed.

2020-Aug-05

Electron Microscope Maker

Steward a Major Incident regarding a Network Outage (WAN provider line outage).

2020-Mar-08

Medical Device Maker

Steward annual fire-code power outage IT shutdown, restart and re-validation, as well as Canon multi-function printer/copier move.

2020-Feb-26

Law Firm

De-rack backup server and prepare for HDD sendback and main unit disposal, troubleshoot UPS PDU, followup HVAC problem.

2020-Feb-19

Medical Device Maker

Structured LAN cabling related to warehouse expansion, move multi-function copier from floor to floor, and troubleshoot 3 wireless AP certificate issues.

2020-Feb-15

Analytical Instruments Maker

Perform regular Windows patch updates on servers, signature updates for anti-virus, and firmware update on Firewall. Install, test, validate the everyday functionality after the updates as a QC step.

2020-Feb-06

Asset Management Firm

Videoconferencing system unneeded parts and cable removal, replacement work.

2020-Feb-02

Electron Microscope Maker

Cisco Unified Call Manager HQ Update, local branch IP Phone operation validation (inbound call, outbound call, voicemail save and retrieve, call hold and transfer, desktop phone screen and LED indicators).

2020-Jan-18

Asset Management Firm

Steward annual fire-code power outage IT shutdown, restart and re-validation, as well as wall mount display construction.

2019-Dec-19

Real Estate Finance Management

Coordinate new Giga-class Internet line installation at sister sites, switchover office connection

2019-Dec-18

Law Firm

Coordinate new WAN line installation (NTT fiber and Colt ONU), switch from old fiber to new

2019-Dec-15

Asset Management Firm

Replace videoconferencing equipment with new Cisco VC devices in two large meeting rooms, perform construction to mount two large-screen monitors on walls

2019-Nov-18

Law Firm

Deploy new backup server (rackmount, connect), photograph and report

2019-Nov-07

Electron Microscope Maker

Switched office WAN user traffic from Orange to AT&T Circuit, then re-validated all aspects of IT

2019-Oct-16

Steel Wire Technology Maker

Deploy replacement Fortinet 100E Firewall, troubleshooting with remote engineer to ensure office Internet speed same or better, validating as needed

2019-Oct-12

Analytical Instruments Maker

Perform regular Windows update on servers, signature update for anti-virus, and firmware update on Firewall. Install, test, validate daily functionality.

2019-Oct-11

Securities Firm

Steward IT shutdown and restart during planned annual building power cycle and testing, working around system migration to Amazon AWS cloud

2019-Oct-02

Steel Wire Technology Maker

Coordinate backup tape drive unit replacement for continually failing device, gracefully shutting down and restarting virtual servers, testing and validating

2019-Oct-02

Medical Device Maker

Deploy Riverbed SteelConnect in datacenter to enhance SD-WAN performance and redundancy, including rack mounting and cabling changes

2019-Oct-01

Medical Device Maker

Manage project for Japan VAT change from 8% to 10% in Navision ERP system, perform validation tests required by compliance related to calculations and client-facing output

2019-Sept-23

Healthcare Firm

Multi-day office layout change equipment move, pull new and remove old cable, re-connect and system validation

2019-Aug-02

Analytical Instruments Maker

Steward system shutdown and restart for annual power maintenance and tests in Yokohama building, IT systems test and daily-use validation

2019-Jul-25

Electron Microscope Maker

ATT WAN circuit activation and Cisco router and switch re-routing after office hours

2019-Jul-06

Medical Device Maker

High-end Projector Installation and Room-to-Room Display Relocation Construction

2019-Jun-18

IT Services Firm

Datacenter Device Removal Work from 5 racks, in preparation for move

2019-May-31

Medical Device Maker

Replace old VC system with Polycom Real Presence 310 and validation of connection to several sites

2019-May-25

Medical Device Maker

Steward annual power outage of office, including startup, test and daily use validation and Hyper-V and VPN failure troubleshooting

2019-May-25

Electron Microscope Maker

Steward annual power outage system shutdown and restart, test and daily use validation and old firewall failure troubleshooting and break-fix

2019-May-09

Electron Microscope Maker

New Router Install x2 and ATT Fiber Line Implementation

2019-Apr-25

Law Firm

Remove Decommissioned Citrix NetScaler Appliance, and re-rack surrounding equipment to make earthquake proof.

2019-Apr-24

Law Firm

Site Survey and planning for 18-year-old out-of-warranty structured cabling replacement project.

2019-Apr-13

Asset Management Firm

Structured cabling tidy-up work during planned power cycle event.

2019-Mar-13

IT Services Firm

Breakfix for failed Yamaha RTX 1210 router/firewall, rewrite of configuration to use latest OS commands.

2019-Mar-10

Medical Device Maker

Steward annual power maintenance of IT for distribution center / warehouse, including startup, test and daily use validation after power up.

2019-Mar-05

Law Firm

Perform rack-mount and connection of Dell SecureWorks iSensor appliance, working with HQ IT team to test and validate.

2019-Mar-02

Asset Management Firm

Steward IT Equipment Shutdown, Restart & Validation, along with some documentation refresh and tidy-up, during Building's Annual Planned Power Outage

2019-Feb-24

Medical Device Maker

Perform office layout change including display mount construction, LAN cabling and move of IT-related devices. Install, test, validate.

2019-Feb-22

Asset Management Firm

Perform IT coordination for internal office layout change, working with furniture and moving vendors, as well as staff (Phase 1)

2019-Feb-16

Electron Microscope Maker

Work with WAN network provider to plan and install router iOS Adaptive QoS Vulnerability security patch.

2019-Feb-16

Analytical Instruments Maker

Perform regular Windows update on servers and firmware update on Firewall. Install, test, validate daily functionality

2019-Feb-15

Intellectual Property Support Firm

Work with Serviced Office to Steward Client IT Equipment Shutdown, Restart & Validation, along with some documentation upgrades, during Building's Annual Planned Power Outage

2019-Feb-13

Medical Device Maker

System test for new medical product launch.

2019-Feb-10

Law Firm

Steward IT Equipment Shutdown, Restart & Validation, along with some documentation upgrades and decommissioned system planning, during Building's Annual Planned Power Outage

2019-Jan-26

Medical Device Maker

Steward IT Equipment Shutdown, Restart & Validation, along with some documentation upgrades and old VC system planning, during Building's Annual Planned Power Outage

2019-Jan-23

Medical Device Maker

RightFAX fax server & gateway device weekend replacement, cut-over and validation at KDDI data center

2019-Jan-22

Asset Management Firm

Raritan KVM device cable tidy-up, organization and labeling, reconnection

2019-Jan-20

Asset Management Firm

Steward IT Equipment Shutdown, Restart & Validation, along with documentation upgrades, switch cable cleanup, and troubleshooting for VC system voice or speaker and phone system Hold problem

2019-Jan-19

Medical Device Maker

Wall-Mounted Presentation Display Relocation, Reconnection, Validation

2018-Dec-27

Medical Device Maker

New Telecommunication-related Product Market Entry Discussion and Research

2018-Dec-14

Law Firm

UPS Power Distribution Unit Password Reset and Reconfiguration

2018-Nov-22

Public Works Firm

User Access Violation Security Audit

2018-Nov-21

Medical Device Maker

New EDI Server Upgrade, Re-Validation

2018-Nov-16

Asset Management Firm

Research and Confirm Viability of Firm's Global Standard UPS Usage in Japan

2018-Nov-15

Electron Microscope Maker

New AT&T Carrier VPN Line and Device Install, Service Turn-up

2018-Nov-12

Analytical Instruments Maker

Steward IT Equipment Shutdown, Restart & Validation, along with some upgrades, during Building's Annual Planned Power Outage

2018-Nov-11

Medical Device Maker

Steward IT Equipment Upgrade, Shutdown, Restart & Validation, Troubleshooting, during Building's Annual Planned Power Outage

2018-Nov-08

Asset Management Firm

New Office Pre-Construction Site Survey for Structured Cabling and Security System

2018-Nov-04

Medical Device Maker

Steward IT Equipment Shutdown, Restart & Validation during Building's Annual Planned Power Outage

2018-Nov-04

Fashion Retailer

Relocation work for Marunouchi retail shop and related IT equipment

2018-Oct-29

IT Services Firm

Cloud database refactoring and enhancement, adding categories to managed documents for better filtering and reporting

2018-Oct-22

Steel Wire Technology Maker

Tokyo WAN failover test and validation with Proximus Co., reporting.

2018-Oct-19

Medical Device Maker

Migrate from old Active Directory and File/Print server, validate and document security compliance

2018-Oct-14

Real Estate Finance Management

Steward IT Equipment Shutdown and Restart during Building's Annual Planned Power Outage ('tis the season)

2018-Oct-06

Financial Advisory Firm

Steward IT Equipment Shutdown and Restart during Building's Annual Planned Power Outage

2018-Sept-30

Medical Device Maker

Internal office desk move for about 20 users

2018-Sept-15

Analytical Instruments Maker

Apply Updates and Patches to Windows Servers, and Firmware Update to Firewall, and re-validate all functions

2018-Sept-12

IT Services Firm

Cloud database enhancement, scripting extraction of future-proof markdown text files from Documents data via API, and committing these to source code control for version comparison.

2018-Sept-08

Financial Advisory Firm

Replace old multifunction devices (printer, copier, scanner) with new models, setup, and test copying, printing and scanning to email and file server folder

2018-Sept-07

Electron Microscope Maker

Urgent Upgrade of Orange IPANEMA network device

2018-Sept-05

Fashion Retailer

Retail Shop device and circuit relocation work in Okayama, number 2

2018-Sept-04

Fashion Retailer

Troubleshoot IP Cameras (Traffic Counters) at Retail Shop in Yokohama

2018-Aug-22

Analytical Instruments Maker

Connect Sales Office WAN via Sophos Firewall Appliance

2018-Aug-06

Electron Microscope Maker

ISR Router Replacement triggered by Cisco Field Notice

2018-Jul-21

Asset Management Firm

Cisco Core switch replacement

2018-Jul-06

Steel Wire Technology Maker

Fortinet Firewall appliance implementation and rack cable cleanup

2018-Jul-03

Fashion Retailer

Retail shop IT device and Internet circuit relocation in Okayama

2018-Jun-22

Medical Device Maker

Distribution center recovery construction after mezzanine removal.

2018-Jun-16

Asset Management Firm

Preparation and Execution of Network Addressing Change and Upgrade 2, Security Audit and Rectification, New FortiNet Firewall Installation

2018-Jun-15

Analytical Instruments Maker

Security Design, then Sophos Firewall Appliances Configuration, Install and Integration, at Japan HQ and Satellite Sites

2018-Jun-11

Medical Device Maker

PM for Navision ERP and Infrastructure upgrade

2018-Jun-03

Financial Advisory Firm

Preparation and Execution of Network Addressing Change and Upgrade, Security Audit and Rectification, New FortiNet Firewall Install

2018-May-22

Electron Microscope Maker

Windows Domain and Email 'PC Migration' Project driven by Company Acquisition

2018-May-19

Analytical Instruments Maker

Apply Microsoft update patches on server in Yokohama office

2018-May-16

Steel Wire Technology Maker

WAN redundancy failover test with Proximus

2018-May-12

Medical Device Maker

Reception TV Mount Construction and Rear Entrance Phone Cabling and Install

2018-May-01

Law Firm

Citrix NetScalar Appliance Install

2018-Apr-21

Asset Management Firm

VC Wall-mount TV and Core Switch Replacement Construction

2018-Apr-20

Fashion Retailer

Hiroshima Retail Outlet Store Opening

2018-Apr-13

Medical Device Maker

Distribution Center Internal Moves, Wifi and Network Construction Activities, due to Japan Fire Code changes

2018-Mar-21

Electron Microscope Maker

Lab Showroom Lighting Construction and Flooring Fix

2018-Mar-18

Medical Device Maker

Annual Power Cycle and Maintenance

2018-Mar-03

Law Firm

Schneider APC Symmetra UPS Replacement

2018-Mar-03

Medical Device Maker

Offsite WebEx Meeting Setup Support for Conference

2018-Mar-01

Medical Device Maker

Impella Committee English Language Website Launch

2018-Feb-11

Law Firm

Annual Power Outage System Shutdown and Restart, Equipment Decommissioning

2018-Feb-01

Medical Device Maker

Impella Committee Mobile-friendly Website Re-Launch

2018-Jan-27

Medical Device Maker

Internal office desk move for about 70 users

2018-Jan-26

Asset Management Firm

Install a new wireless access point to replace their current consumer class one

2018-Jan-23

Medical Device Maker

International IP Phone Service cutover to local IP Phone Service from Denphone.

2018-Jan-20

Analytical Instruments Maker

Additional LAN Cable Installation Project

2018-Jan-13

Medical Device Maker

Internal Office Layout Change and Cabling

2018-Jan-11

Analytical Instruments Maker

Secure Windows server "inherited" from other vendor, by applying years worth of patches

2017-Dec-26

Medical Device Maker

Research Toll Free 0120 "FreeDial" Number Options

2017-Dec-08

Medical Device Maker

Cutover Tokyo Firewall from Virtual to Physical

2017-Dec-05

Law Firm

Remove Previous PBX Equipment from Rack and Prep for Send-back

2017-Dec-03

Law Firm

Security Appliance Installation / HDD Onsite Destruction

2017-Nov-26

Intellectual Property Support Firm

Remove LAN Cable post-move

2017-Nov-17

Intellectual Property Support Firm

Office Move Project

2017-Nov-13

Analytical Instruments Maker

Planned Power Maintenance and Windows Update on Servers

2017-Nov-10

Analytical Instruments Maker

Cisco SX10 Videoconference System Installation

2017-Nov-10

Securities Firm

Replace Switches and Upgrade SonicWall Firewall Firmware

2017-Nov-01

Law Firm

EMC AX4-5i Storage Array Removal

2017-Oct-20

Intellectual Property Support Firm

Internet Connection Construction and Media Converter Installation

2017-Oct-19

Law Firm

Cisco Video-conference System (MX300) Installation

2017-Oct-10

Academic Society

Japan VAD Council Japanese-language Website Launched

2017-Oct-04

Law Firm

Install "Pure Storage" Array HBA Cards to Prep for EMC Replacement

2017-Sept-29

Steel Wire Technology Maker

Border Router Replacement

2017-Sept-11

Medical Device Maker

Deploy 2nd Palo Alto Firewall

2017-Aug-27

Asset Management Firm

Additional LAN Cabling

2017-Aug-11

Analytical Instruments Maker

Windows update and patch for server

2017-Jul-25

Asset Management Firm

Disaster Recovery Site Raritan Device Replacement

2017-Jul-22

Analytical Instruments Maker

New Server Installation

2017-Jul-18

Medical Device Maker

Initial Quick Launch of "Council for Clinical Use of Ventricular Assist Device Related Academic Societies, IMPELLA committee" Japanese-language Website

2017-Jul-01

IT Services Firm

Patch Cabling Replacement in Server Room

2017-Jun-13

Law Firm

New cabling for Wireless AP & Conference room

2017-May-25

Asset Management Firm

Security device replacement, de-rack re-rack

2017-Apr-11

Steel Wire Technology Maker

WAN equipment replacement, backup circuit upgrade, network firmware upgrades

2017-Jan-05

Electron Microscope Maker

Major office and lab construction, office move and consolidation

2016-Dec-01

Medical Device Maker

Japanese Language Website Launch

2016-Oct-17

Medical Device Maker

Partially-Furnished Office Move Project

2015-Mar-31

Medical Device Maker

New Konica MFP Installation

2013-Jul-26

Medical Device Maker

Japan Website Launch

2012-Apr-28

Law Firm

Tokyo DC Refresh and Earthquake Proofing, and APC Symmetra UPS Replacement

2012-Apr-14

Electron Microscope Maker

New AV Video Conference Equipment Construction

2012-Apr-05

Electron Microscope Maker

New AV Video Conference Equipment Construction Prep

2012-Mar-13

Electron Microscope Maker

Perform Site Survey for New AV Video Conference Equipment Construction

2012-Mar-08

Medical Device Maker

Create an Independent Direct Number and Voicemail Box for HR

2012-Mar-04

Electron Microscope Maker

New Wireless Access Points and Controllers

2012-Mar-01

Steel Wire Technology Maker

Pre-cabling Site Survey

2012-Feb-28

Medical Device Maker

Logistics Center LAN Cabling Relocation, Re-pull Work

2006-Aug-01

Medical Device Maker

Japan PM for Rollout of BaaN ERP and ARGO21 EDI to replace Legacy AS/400 System